Atlas Energy Solutions Announces Third Quarter 2026 Results Austin, TX – November 2, 2026 – Atlas Energy Solutions Inc. (NYSE: AESI) (“Atlas” or the “Company”) today reported financial and operating results for the third quarter ended September 30, 2026.
Third Quarter 2026 Highlights
• Total revenue of $267.8 million, net loss of $45.1 million and Adjusted EBITDA of $30.3 million
• Net cash generated from operating activities of $23.4 million and Adjusted Free Cash Flow of $25.3 million
• Announced two Cost Reimbursement Agreements ("CRA") with a leading frontier AI lab supporting balance-of-plant equipment and an incremental 283 megawatts ("MW") to enable two significant data center projects
• Completed $424 million Senior Secured Bridge Facility provided by Goldman Sachs and Barclays subsequent to quarter end
• Positioned to enter 2027 with more than 23 million allocated tons
John Turner, President & CEO, commented, “During the third quarter, we took significant steps in our methodical approach to building out our behind-the-meter power business. Our plan is simple: secure the equipment, sign the contracts, lock in long-term financing, and deliver. Our CRAs with a leading frontier AI lab and our new $424 million bridge facility have significantly reduced the near-term financing and supply chain risk on the equipment for two significant data center projects we are currently negotiating. Our first behind-the-meter project in Socorro, Texas, remains on track to come online at the end of the first quarter of next year, and it shows what Atlas does best: build quickly, operate reliably, and deploy power where it’s needed.
In our sand business, we made a deliberate choice during the quarter to hold the line on pricing rather than chase uneconomic bids. As expected, that reduced our third quarter sales volumes. Our commercial team has since backfilled those volumes for the fourth quarter and, with line of sight to more than 23 million allocated tons for 2027, we expect sequential improvement across all of our business lines during the fourth quarter.”
Third Quarter 2026 Financial Results Third quarter 2026 revenue was approximately $267.8 million, comprised of product revenue of $97.9 million, service revenue of $140.8 million and power rental revenue of $29.1 million. Total proppant sales volume during the quarter were 5.4 million tons. Our average sales price for proppant for the third quarter was approximately $16.93 per ton. Included in our product revenue during the period is roughly $3.5 million of power equipment sales and $2.8 million of logistics related sales.
Third quarter costs of sales (excluding DD&A) were $215.5 million, consisting of $72.1 million in proppant plant and logistics operating costs, $2.1 million from power equipment costs, $128.7 million of service costs, $8.8 million in rental costs, and $3.8 million in royalties. Within our logistics operating costs, we also recognized $1.4 million during the quarter tied to the cessation of operations in a particular region.
Selling, general and administrative expenses for the third quarter of 2026 were $38.8 million.
Net loss for the third quarter of 2026 was $45.1 million, and Adjusted EBITDA for the third quarter of 2026 was $30.3 million.
Liquidity, Capital Expenditures and Other As of September 30, 2026, the Company’s total liquidity was $116.7 million, which was comprised of $22.3 million in cash and cash equivalents, and $94.4 million of availability under the Company’s 2023 ABL Credit Facility.
Subsequent to quarter end, the Company entered into a $424.0 million senior secured bridge facility and as of October 23, 2026, the Company’s estimated total liquidity was $499.4 million, which was comprised of $152.2 million of cash and cash equivalents, $252.8 million of availability under the bridge facility that is designated for certain purchase obligations and $94.4 million of availability under the Company’s 2023 ABL Credit Facility.
Future Guidance The Company is providing financial guidance for the fourth quarter of 2026. Guidance is based on current outlook and plans and is subject to a number of known and unknown uncertainties and risks and constitutes a “forward-looking statement” within the meaning of Section 21E of the Securities Exchange Act of 1934, as amended (the "Exchange Act") as further described under the Cautionary Statement below. Actual results may differ materially from the guidance set forth below.
Looking ahead to the fourth quarter, we expect sequential improvement in every segment of our business. For the fourth quarter, we currently expect Adjusted EBITDA in the range of $40 million to $50 million.
Conference Call Information The Company will host a conference call to discuss financial and operational results on November 3, 2026 at 9:00am Central Time (10:00am Eastern Time). Individuals wishing to participate in the conference call should dial (877) 407-4133. A live webcast will be available at https://ir.atlas.energy/ . Please access the webcast or dial in for the call at least 10 minutes ahead of the start time to ensure a proper connection. An archived version of the conference call will be available on the Company’s website shortly after the conclusion of the call.
About Atlas Energy Solutions Atlas Energy Solutions Inc. (NYSE: AESI) is a leading energy solutions provider, unlocking energy that powers the world’s critical infrastructure. For companies requiring power where grid utilities are unavailable, Atlas can help customers overcome the schedule and capital expense barriers that hinder project and operational success. For oil & gas producers, Atlas helps companies overcome disruptive operational and technical challenges to maximize oilfield completions and operations. From large scale private grid power systems to the world’s most advanced frac sand delivery networks, Atlas delivers the engineering, technology and turnkey project execution expertise that turns energy constraints into advantages.