EX-99.2 a261112firstquarterfy27r.htm EX-99.2 a261112firstquarterfy27r Tamboran Resources Corporation ARBN 672 879 024 Tower One, International Towers Suite 1, Level 39, Barangaroo Avenue, Barangaroo NSW 2000, Australia +61 2 8330 6626 www.tamboran.com First quarter activities report for period ended September 30, 2026 Highlights • During the quarter, Tamboran and Daly Waters Energy (DWE) became the first parties to sell gas from the Beetaloo Basin. Tamboran delivered total net gas sales of 0.31 Bcf and earned revenue of US$1.8 million. First cash inflows were received in early November 2026. • Delivered average flow rate of 10.2 MMcf/d over an interrupted 720-hour period over ~5,500 feet from the SS2-2H ST1 well, a material uplift in productivity following testing in 2025. After being shut in for a year, the well produced minimal water flow back and demonstrates a typical well deliverability post-clean-up. • Delivered average IP30 rates of 8.8 and 10.0 MMcf/d from the SS2-3H and -5H wells respectively, confirming performance in-line with prior testing. Both wells were tied in without soaking and are sustaining relatively high bottomhole pressures, suggesting increased deliverability as the wells continue to clean up, in-line with other US shale basins. • Three-well drilling program on the SS1 pad was completed using the Helmerich & Payne (NYSE: HP) super- spec FlexRig® Flex 3 Rig, with ~29,000 feet of combined usable lateral. Stimulation activities using the Liberty Energy (NYSE: LBRT) frac fleet are planned for 4Q 2026. • Santos (ASX: STO) commenced a two-well appraisal program in EP 161, in which Tamboran holds a 25% non-operated interest. The Jibera South 1H DW1 (JS-DW1) pilot hole reached TD and logged all Velkerri Shale formations in-line with expectations. • Cash balance and near-term inflows totaling US$180 million as of September 30, including Tamboran’s 50% share of restricted cash. Net drawn debt of US$37 million, associated with the construction of the SPCF, with undrawn debt of US$26 million (net Tamboran) remaining. Key metrics 1Q FY26 4Q FY26 1Q FY27 Change (%) Production Bcf - - 0.31 100% Sales Revenue(1) US$m - - 1.8 100% EBITDAX(2) US$m (6.1) (5.7) (14.5) 154% Cash Balance(3) US$m 40 225 165 (27%) (1) Sales Revenue and direct costs for the Pilot Project were capitalized to the balance sheet during the quarter as the Project has not reached Practical Completion of the SPCF nor Commercial Operations Date under the GSA. Not yet reflected in the EBITDAX. (2) EBITDAX is a non-US GAAP metric which means Earnings Before Interest Tax Depreciation Amortization and Exploration Expense and is a proxy for operating cash flows. (3) Cash balance includes Tamboran’s net portion of restricted cash of US$4.8 million. ANNOUNCEMENT November 12, 2026 Tamboran Resources Corporation (NYSE: TBN; ASX: TBN)
2 Tamboran Resources Corporation Managing Director and Chief Executive Officer, Mr. Todd Abbott, said: “This quarter Tamboran and Daly Waters Energy made history by becoming the first companies to sell gas from the Beetaloo Basin. Gas from the Beetaloo is now a major contributor to the domestic Northern Territory market. “During our first period of gas sales, we delivered 0.31 Bcf and generated US$1.8 million in revenue. These numbers are expected to increase as we complete the commissioning phase and enter the take-or-pay contract with the Northern Territory Government in early 2027. “Long duration flow testing of wells on the SS2 pad commenced in September. Initial rates confirm the successful deliverability demonstrated in prior testing of wells in the basin. These results support our view that declines remain relatively low and rates should rise as the wells continue to clean up. “Importantly, the SS2-2H ST1 well shows what we believe these wells can deliver once cleaned up. The well was reopened with minimal water flow back and delivered an average rate of 10.2 million cubic feet per day over 720 hours of interrupted production. This is a material step up in productivity from the initial 90-day flow period in 2025 and in-line on a normalized basis with the SS-1H result from 2024. “The SS2-3H and SS2-5H wells have delivered average IP30 rates of 8.8 and 10.0 MMcf/d respectively over 10,000 feet. Both wells were tied in without soaking and are sustaining relatively high bottomhole pressures, which suggests there is more deliverability to come as the wells continue to clean up. “The 2027 calendar year is about building the resource across our 2.8 million net prospective acre Beetaloo Basin position. This includes step-out drilling and flow testing within the Beetaloo Central Development Area (BCDA) and EP 161 acreage positions. We expect to undertake additional wells in our Orion acreage once we finalize our strategic partnership.” Capital Expenditure Incurred capital expenditure of US$56.9 million relating primarily to drilling and stimulation activity on the SS2 pad, drilling activity on the SS1 pad, drilling in the EP 161 permit and construction of the Sturt Plateau Compression Facility (SPCF) (inclusive of financing costs). Key metrics 1Q FY26 4Q FY26 1Q FY27 Change (%) Exploration & Evaluation US$m 17.1 34.2 48.6 42% Assets Under Construction US$m 5.1 7.2 8.1 13% Land & Buildings US$m - - 0.2 100% Total Capital Expenditure US$m 22.2 41.4 56.9 37% Note: Capital expenditure is Tamboran’s net share of costs, with net revenue and costs of the Pilot Project offset against the Exploration & Evaluation asset. Reported GAAP financials include the share of Daly Waters Energy, LP and Daly Waters Infrastructure, LP.
3 Liquidity Key metrics 1Q FY26 4Q FY26 1Q FY27 Change (%) Cash Balance US$m 40 225 165 (27%) Drawn Debt US$m - (30) (37) 23% Net Cash / (Debt) US$m 40 195 128 (34%) Note: Cash balance differs from the GAAP financials due to removal of Daly Waters Infrastructure, LP net share of restricted cash. Capital Structure No new shares have been issued since the release of the 4Q FY26 report. Minor transfer of CHESS Depositary Interests (CDIs) to Common Stock. Key metrics 1Q FY26 4Q FY26 1Q FY27 Change (%) Common Stock 12,922,097 28,280,039 28,337,692 0.2% CHESS Depositary Interests (CDI) 1,514,354,400 1,335,993,400 1,324,462,800 (0.9%) Total Common Stock (Equivalent) 20,493,869 34,960,006 34,960,006 - Restricted Stock Units - 848,724 848,724 - Options 179,250(1) 369,084 369,084 - Fully Diluted Stock (Common Stock) 20,673,119 36,177,814 36,177,814 - Note: CHESS Depositary Interests 200:1. (1) 179,250 Common Stock equivalent options (35,850,000 unlisted CDI options) expired on May 26, 2026, as disclosed in the Company's Appendix 3H lodged with ASX on June 15, 2026. Webcast details Tamboran’s Managing Director and Chief Executive Officer, Mr. Todd Abbott will host a webcast commencing at 5:00pm EST on Thursday November 12, 2026 (9:00am AEDT on Friday November 13, 2026). Access to the live audio webcast for the conference call is available via Tamboran’s website at https://ir.tamboran.com/.
4 Operations Overview Shenandoah South Pilot Project Tamboran 44.375 per cent working interest in 20,239 acres and operator of the Northern Pilot Area(1) In July 2026, Tamboran and DWE (together the Beetaloo Joint Venture (BJV)) completed stimulation, cleanout and completion activities on the SS2-3H, -4H and -5H wells on the SS2 pad. The program was the first three-well zipper stimulation and the largest campaign conducted in the Beetaloo Basin to date, with 178 stages placed across ~30,000 lateral feet within the Mid Velkerri B Shale using the Liberty Energy frac fleet. The campaign averaged 6.7 stages per day and set Beetaloo Basin records, with pumping operations exceeding 20 hours per day and 12 stages completed in a single day. The BJV also placed locally produced Beetaloo Red Sand (BRS) in 10 stages along the lateral of the SS2-5H well, the first deployment of BRS in the basin. Tracers were deployed to compare the performance of these stages against stages using imported sand. Long-duration flow testing of wells on the SS2 pad commenced in September 2026. Initial rates confirm the positive deliverability demonstrated in prior testing of wells in the basin. The SS2-2H ST1 well delivered an average rate of 10.2 MMcf/d over 720 hours of interrupted production across ~5,500 feet of lateral, materially better than the initial 90-day flow period. The well normalized to 18.4 MMcf/d over a 10,000-foot horizontal, in-line with the original SS-1H well, which was flow tested in 2024. The SS2-2H ST1 well demonstrates deliverability potential of a cleaned-up well. The SS2-3H and SS2-5H wells delivered average IP30 rates of 8.8 and 10.0 MMcf/d, respectively, and both continue to produce 300 to 500 barrels of water per day, as the wells were tied into the SPCF immediately following the stimulation campaign earlier this year. Both wells are sustaining relatively high calculated bottomhole pressures, which suggests further deliverability to come as the wells clean up. Observations from subsurface work indicate that well delivery materially increases as water used in the stimulation program is recovered or imbibes into the formation over time. Based on these initial results, Netherland, Sewell & Associates, or NSAI, has estimated a P50 EUR of 17 Bcf per 10,000-foot lateral. The SS2-5H well included 10 stages stimulated with BRS. Early performance shows no degradation in deliverability from using local sand, providing confidence in its deployment in future wells. The BJV plans to further test BRS on at least one well during the SS1 pad stimulation program. Tamboran 44.375 per cent working interest in 20,230 acres of the Southern Pilot Area(1) During the quarter, Tamboran and DWE commenced the three-well drilling program on the SS1 pad using the Helmerich & Payne (H&P) super-spec FlexRig® Flex 3 Rig. (1)Working interests include impact of farmout to Daly Waters Energy, LP, announced in March 2026.
5 The SS1-6H and SS1-4H wells were successfully drilled and cemented to total depth (TD) over 32 and 24 days, including 9,434 and 9,635-foot usable horizontal section within the Mid Velkerri B Shale, respectively. The SS1-2H well encountered a downhole issue after drilling a lateral section of 12,631 feet, which required a side- track. The side-track well was drilled in early November 2026, with a usable lateral section of 9,989 feet. The program remains within the contingency capital expenditure budget. The BJV plans to stimulate the three wells on the SS1 pad using the Liberty frac fleet during the December 2026 quarter and over the wet season. The wells are expected to be tied back to the SPCF during 1Q 2027. Sturt Plateau Compression Facility (Tamboran 50%, Daly Waters Infrastructure (DWI) 50%) Construction of the SPCF, a 50/50 joint venture with Daly Waters Infrastructure (DWI), was completed in August 2026. The SPCF was constructed on time and is forecasted to come in ~US$10 million below budget when it reaches Practical Completion. The facility commenced processing gas and delivered first gas sales into the Northern Territory gas market in early September 2026. The facility is currently undergoing commissioning activities, including tuning control systems and refining equipment settings. Tamboran and DWE receive a discounted price (75% of the contract gas price) until the take-or-pay gas sales contract commences, reflecting the interruptible nature of supply during the current period. EP 161 Santos 75 per cent working interest and operator, Tamboran 25 per cent working interest During the September quarter, Santos, the operator of the EP 161 permit, commenced the two-well drilling program to delineate further resources across the Beetaloo East depocenter. The JS-DW1 well spudded in early September using the Ensign 971 rig, reaching a TD of ~11,300 feet on the pilot vertical hole. The well successfully intersected all Velkerri Shale formations in October, with results in-line with Tamboran’s expectations. Drilling of the 10,000-foot horizontal section within the Velkerri B Shale has since commenced. On completion of the JS- DW1 well, the rig is planned to mobilize to the Newcastle South DW1 (NS- DW1) location ~11 miles to the southeast for the drilling of a second 10,000-foot horizontal well. Both wells are planned to be stimulated across up to 60 stages per well and flow tested during 2027.
6 Commercial and Corporate Update MOU with Liberty Energy to extend Beetaloo partnership In September 2026, Tamboran signed a non-binding Memorandum of Understanding (MOU) with Liberty Energy (NYSE: LBRT) to extend its hydraulic fracture stimulation and wireline services agreement in the Beetaloo Basin. The proposed extension covers an initial three-year term from 2026 to 2029, with a mutual option to extend by a further two years to 2031. The parties are now documenting the terms, and any extension is subject to final agreements being signed. Liberty plans to start introducing lower-emissions pumping equipment to the Beetaloo fleet from 2027. The companies also plan to jointly assess a next-generation, lower-emissions completions fleet over the term of the extension. The MOU also provides Tamboran with priority access to other Liberty services as they are introduced to Australia. These include gas processing and conditioning and remote gas-fired power generation through Liberty Power Innovations, PropX sand slurry delivery and collaboration on the development of local proppant supply. Falcon Australia minority interests On November 10, 2026, Tamboran paid A$4.1 million into the Falcon Oil & Gas Australia Limited (Falcon Australia) account and became the sole shareholder of Falcon Australia. These funds, which represent the payment due to former Falcon Australia shareholders, are held on trust for those shareholders. Falcon Australia’s registrar, Boardroom, has written to each former shareholder requesting bank account details and payment instructions. Former shareholders will be paid A$1.77994 per share, in proportion to their previous holdings. Tamboran will keep records of all payments and work with ASIC on any unclaimed funds, as required under the Corporations Act 2001 (Cth). Managing Director appointment On October 19, 2026, Mr. Todd Abbott was appointed Managing Director of Tamboran, in addition to his role as Chief Executive Officer. The appointment follows his appointment as Chief Executive Officer in January 2026 and formalizes his executive leadership at Board level as the Company moves from appraisal into development. Notice of Annual General Meeting Tamboran will host its 2026 Annual Meeting of Stockholders on Thursday November 19, 2026 at 4:00pm Central Standard Time (Friday November 20, 2026 at 9:00am AEDT). The meeting will be held online and be completely virtual via http://www.virtualshareholdermeeting.com/TBN2026
7 Permits At the end of the quarter, Tamboran and its subsidiaries held the following prospective acreage positions. Permits Gross Prospective Acres Interest Net Prospective Acres Northern Pilot Area 20,239 44.38%* 8,982 Southern Pilot Area 20,230 44.38% 8,978 Orion Block 493,229 78.00%* 384,719 Beetaloo Central Development Area (BCDA) 316,131 10.00% 31,613 Andromeda Block 218,176 92.00%* 200,722 Pegasus Block 536,669 100.00%* 536,669 Draco Block 914,839 100.00%* 914,839 DW OTD Area 813,460 22.50% 183,029 DW Plains Area 281,633 12.50% 35,204 DW Arnold Area 525,740 22.50% 118,292 DW Carpentaria Area 202,931 22.50% 45,659 EP 161 512,000 25.00% 128,000 Maverick Block (EP 136) 207,000 100.00%* 207,000 Total 5,062,277 2,803,705 *Denotes operator interest following the completion of the Checkerboard. Note: Working interests also include impact of (i) the Acreage Sale to Daly Waters Energy, LP, announced in May 2025 and subject to completion of certain conditions precedent, (ii) Acreage Realignment Agreement with Daly Waters Energy, LP, announced in November 2025, and (iii) the farmout to Daly Waters Energy, LP, announced in March 2026.
8 This announcement was approved and authorized for release by Todd Abbott, the Managing Director and Chief Executive Officer of Tamboran Resources Corporation. For further information, please contact: Investor enquiries: Chris Morbey, Vice President – Corporate Development and Investor Relations +61 2 8330 6626 Investors@tamboran.com Media enquiries: +61 2 8330 6626 Media@tamboran.com About Tamboran Resources Corporation Tamboran Resources Corporation (NYSE/ASX: TBN) is a growth-driven independent natural gas exploration and production company. Tamboran is focused on an integrated approach to the commercial development of the natural gas resources in the Beetaloo Basin located within the Northern Territory of Australia. Through its subsidiaries, Tamboran holds approximately 2.8 million net prospective acres and is the largest acreage holder in the Beetaloo Basin depocenter.
3 Investment highlights Systematically de-risking one of the largest undeveloped gas projects in the world Tamboran’s Investment Case New production company Transition to producer with first gas sales achieved in September 2026; TJ/d (gross) from Pilot Project contracted to the Northern Territory Government at fixed price, CPI escalated Proven team Proven Board and Management with operational and commercialization experience to unlock large-scale shale developments Partners accelerating lessons Tamboran has brought in strategic partnerships (all equity holders) with Helmerich & Payne (NYSE: HP), Liberty Energy (NYSE: LBRT) and Baker Hughes to accelerate incorporation of lessons from the US shale industry Most experienced operator Tamboran’s operations team has been involved in the Beetaloo Basin for over a decade, operating 11 horizontal wells across the basin, the most by any operator Basin-scale acreage position Largest Beetaloo Basin acreage holder, owning majority of the basin’s prospective area with 2.8 million net prospective acres and multiple stacked benches across two key depocenters Multiple gas markets Three highly attractive markets trading at premiums to the US Henry Hub price and potential future exposure to international LNG Tamboran’s ~2.8 million prospective acres (net) Beetaloo depocenter *Denotes operator interest following the completion of the Checkerboard. Working interests also include impact of (i) the Acreage Sale to Daly Waters Energy, LP, announced in May 2025 and subject to completion of certain conditions precedent, (ii) Acreage Realignment Agreement with Daly Waters Energy, LP, announced in November 2025, and (iii) the farmout to Daly Waters Energy, LP, announced in March 2026. EP 161 (25%)
Evolution of Beetaloo Basin development Years of subsurface de-risking underpin disciplined capital allocation to resource delineation 4 Evaluate Subsurface and Implementing Learnings − Establish long-term flow testing through the SS Pilot Project − Generate early cash flow to support the balance sheet − Evaluate local markets for incremental production and revenue growth − Apply US learnings to demonstrate well deliverability − Test local sand supply to demonstrate pathway to future cost reduction Resource Delineation and Commercial Pathways − Disciplined capital allocation to grow upstream resource supporting infrastructure buildout − Focus on core acreage with key partners (Orion, BCDA, EP 161) − Leverage EP 161 activity across Tamboran operated Andromeda and Maverick acreage − Grow production incrementally into the NT and Mt Isa markets − Greater confidence in local sand performance to lower long-term development costs Development and Efficiencies − Unlock material production growth − Step up drilling and stimulation to continuous operations − Scale economies from higher activity, lower unit costs − Build processing and pipeline infrastructure Continued Growth and Capital Allocation − Optimize operations across producing assets − Build additional market access − Continued focus on capital efficiency and disciplined capital allocation 2023 – 2026 2027 – 2028 2029 – early 2030s Mid-2030s and beyond Capital disciplined approach to de-risking Tamboran’s Beetaloo Basin development ✓
1Q FY27 highlights Flow results affirm expectation and confirm the deliverability of Velkerri B Shale wells Delivered first gas sales from the Beetaloo Basin SS2-3H and -5H wells confirmed prior testing with average IP30 rates of 8.8 and 10.0 MMcf/d, respectively while still unloading(1) SS2-2H ST1 lateral delivered an IP30 of 10.2 MMcf/d over a ~5,500-ft lateral, ~50% higher than 2025 testing, demonstrating deliverability of a cleaned up well Completed drilling of three wells on the SS1 pad. Non-operated two-well appraisal program on EP 161 underway Continued to progress strategic partnership discussions 1Q FY27 key statistics 0.31 Bcf Net production to Tamboran(2) (~24.8 MMcf/d average gross daily volume(3)) US$1.8 million Generated from gas sales 98% NT Government nominations met, demonstrating strong SPCF performance(4) ~US$180 million Pro forma cash balance, including US$165 million cash at September 30, 2026(5) and US$15 million near-term inflows(6) (1) Refer to Appendix for disclosures under ASX Listing Rule 5.30 Wells experienced short-term interruptions due to facility downtime and reduced nominations. (2) Tamboran’s net share of production was 51.05%. (3) Gas sales currently constrained by Northern Territory nominations, (4) Gas delivered against nominations between September 5 and October 31, 2026. (5) Reported cash balance of US$169.7 million less Daly Waters Infrastructure, LP 50% share of restricted cash (6) Near term cash inflows include US$15 million from acreage sale to DWE (announced May 2025) which remain subject to satisfaction of certain conditions precedent. 5
− Well rates confirm positive deliverability in-line with previous testing − SS2-2H ST1 shows indicative deliverability of a cleaned up well o Average rate of 10.2 MMcf/d over 720 interrupted hours across ~5,500 ft (normalized to 18.4 MMcf/d per 10,000 feet), in-line with the SS-1H normalized rate of 19.5 MMcf/d(1) o Material increase in productivity than when shut in after the 2025 test (10.2 vs 7.2 MMcf/d), at a higher wellhead pressure (~1,100 vs 906 psi) − SS2-3H and -5H delivered IP30 rates of 8.8 and 10.0 MMcf/d, respectively o Continuing to produce 200 - 400 bbl/d of stimulation water o High bottomhole pressures have potential to increase deliverability as wells clean up − SS2-1H and -4H wells are yet to be completely opened and have been managed as balancing wells during the initial commissioning period − Results continue to suggest that, as stimulation water is recovered or imbibes into the formation, well deliverability improves − Early performance of the SS2-5H well is showing no degradation in deliverability using the local BRS, giving confidence in deployment in future wells Well performance Confirming low decline and improvement in productivity as wells are cleaned up | SS2-2H ST1 shows material improvement 6 SS2 Well Pad Performance IP30 (MMcf/d) Stimulated length (feet) IP30 (Normalized) (MMcf/d/1,000 ft) IP30 (Normalized) (MMcf/d/10,000 ft) Wellhead Pressure (psi) SS2-1H Well produced intermittently as needed for nominations SS2-2H ST1 Well produced intermittently as needed for nominations SS2-3H 8.8 10,260 0.9 8.6 ~910 SS2-4H Well produced intermittently as needed for nominations SS2-5H 10.0 10,246 1.0 9.7 ~920 (1) As announced February 26, 2026. SS-1H achieved 3.2 MMcf/d over a 1,644-ft lateral section, normalized to 19.5 MMcf/d over 10,000 feet. 0 2 4 6 8 10 12 14 16 1 6 11 16 21 26 A v e ra g e f lo w r a te ( M M c f/ d ) Days Well flow rates over 30 days (Rolling 5-day Average) SS2-3H (10,260-ft) SS2-5H (10,246-ft) Note: Testing was interrupted by changes to daily nominations and typical plant commissioning processes Choked back to reflect nominations Opened up
Shenandoah South Pilot Project Successfully executed infrastructure construction and stimulation activities, achieving first gas sales on time and within budget 7 − Completed construction of the SPCF, forecasted to be ~US$10 million under budget − Targeting completion of commissioning of the SPCF in 4Q 2026 − Revenue to be received at 40 TJ per day regardless of nominations once Take-or-Pay contract commences with the NTG, forecasted to be in 1Q 2027 − Beetaloo Basin stimulation activities on the SS2 pad o SS2-3H, 4H and 5H wells zipper frac’d with 184 stages (>30,000 stimulated feet) o SS2-5H well completed with 10 stages of local Beetaloo Red Sand; performance consistent with other stages − Completed three well drilling program on SS1 pad o SS1-4H and -6H wells drilled with 9,434 and 9,635 usable lateral feet, within budget o SS1-2H side-track required due to down hole issue following drilling of the 12,631- foot lateral section o SS1-2H ST1 successfully drilled with 9,989 usable lateral feet o SS1 wells planned to be stimulated during 4Q 2026 / 1Q 2027, subject to weather o Three well program remains on budget Balance sheet 8 (1) Cash balance at September 30, 2026 includes restricted cash of US$4.8 million net to Tamboran (US$9.6 million gross) to be used for future commitment fees, interest and debt payments relating to the SPCF syndicated debt facility. (2) Cash flow from investing includes cash associated with drilling activity and infrastructure; Cash flow from investing adjusted for receivables relating to cash calls due from JV partners and DWE’s share of restricted cash. (3) TBN share of debt proceeds drawn. (4) Includes lease payments and FX adjustments. Maintain strong balance sheet with ~US$180 million cash(1) and expected near-term inflows 165 180 (10) (58)(2) 225 7(3) 2(4) Cash Balance (June 30, 2026) Cash Flow from Operations Cash Flow from Investing Proceeds from Debt Other Cash Balance (Sept. 30, 2026) Checker Sale to DWE Pro Forma Cash Balance U S $ m il li o n 1Q FY27 Change in Cash Balance